Tunnelsonline:SR99掘进机贯通隧道
来源:Tunnelsonline 发布:2017/5/19 浏览:

 一年以前,SR 99隧道工作人员面临最大的挑战:阿拉斯加方式高架桥下方,盾构机正在奋力掘进,以替换老旧的高架桥。而今年的4月4日,随着高架桥和超过9,270英尺的新隧道贯通,随着西雅图中心附近的SR99盾构机的贯通,Bertha重见天日。

The TBM's 1.7-mile drive beneath Seattle came to a successful end 64 years to the day since the viaduct first opened to traffic. Led by the Washington State Department of Transportation (WSDOT), and designed and built by contractor Seattle Tunnel Partners, the tunnel project will move a two-mile section of SR 99 underground when it wraps up in early 2019. Crews will then demolish the viaduct, clearing the way for the city’s new waterfront.

“This is a historic moment in our state’s transportation history,” Gov. Jay Inslee said. “Innovation and perseverance are the engines that keep Washington in the forefront. There is still more work ahead but this moment is one worth celebrating.”

Crews will spend the next several days removing steel support braces that stand between the TBM and the interior of the 90ft-deep disassembly pit. When the braces are gone, crews will drive the machine into its final position and begin cutting it into pieces for removal. As owner of the machine, the contractor will determine which pieces could be salvaged for use on other projects or recycled.

“We were always confident that we would successfully complete the tunnel drive,” Seattle Tunnel Partners Project Manager Chris Dixon said. “The dedication and commitment of everyone on the Seattle Tunnel Partners team has been exceptional, and we wouldn’t be at this milestone without the hard work of our crews. We look forward to continuing this outstanding progress through project completion.”

STP still has significant work to complete before the tunnel opens, WSDOT said. Crews must finish building the double-deck highway within the circular walls that were built by crews inside the tunneling machine. Mechanical and electrical systems, plumbing and safety features also must be installed.

Even as crews are installing these systems, crews will begin the extensive task of testing and commissioning the tunnel to ensure it’s ready for traffic. Inspectors will individually test more than 8,500 separate components before testing each of the tunnel’s various systems as a whole.

“This truly is a remarkable feat of engineering,” Transportation Secretary Roger Millar said. “There’s still work to be done, but the individuals working on this job should be proud of this accomplishment.”

Over the next several years, the City of Seattle’s Waterfront Seattle project will build new public space and a surface boulevard in the place of the double-deck viaduct, which is scheduled for demolition in 2019.

“Today is a major construction milestone in our plan to reclaim Seattle’s waterfront,” Seattle Mayor Ed Murray said. “We are one step closer to taking down the viaduct to make way for a reimagined waterfront and surrounding downtown neighborhood. We will build a waterfront for pedestrians, transit and sensible car trips without a freeway wall casting a shadow over our vision of a well-connected 21st century city.”

“The new tunnel will provide fast, reliable travel for transit and freight past downtown traffic, and reunite the city with its waterfront,” said Constantine. “The breakthrough highlights what we can accomplish when we think big, act boldly, and embrace the 'can-do' tradition of our region.”

Port of Seattle Commission Commissioner Courtney Gregoire said the tunnel will work with the new waterfront surface street to accommodate freight traffic.

“This Alaskan Way route is essential to a strong port and linking our industrial lands between SODO and Ballard,” Gregoire said. “Strong, vibrant transportation connections are essential to keep our economy growing and creating middle-class jobs.”

Background on tunneling machine repairs
Manufactured in Japan by Hitachi Zosen Corp., the TBM arrived in Seattle in April 2013. The machine was launched from a pit near the stadiums in July of that year. In December 2013, STP stopped mining after measuring increased temperatures in the machine.

After an investigation, STP discovered damage to the machine’s main bearing. Crews completed repairs and resumed mining in December 2015. The cause of damage to the tunneling machine is in dispute and is currently in litigation. Neither WSDOT nor STP will comment further on ongoing legal issues.

隧道网版权及免责声明:

凡本网注明“来源:隧道网”的所有作品,版权均属于隧道网,未经本网授权,不得转载、摘编或以其它方式使用上述作品。已经本网授权使用作品的,须在授权范围内使用,并注明“来源:隧道网”。违反上述声明者,本网将保留追究其相关法律责任的权利。凡本网来源注明为非隧道网的作品,均转载自其它媒体,转载目的在于传递更多信息,该文章仅代表作者观点,并不代表本网赞同其观点或对其真实性负责,请读者自行核实相关内容,仅作参考。如因作品内容、版权和其它问题请与本网联系。

相关文章
大事记
BIG EVENT
2019
2月2日,SR99隧道正式开通。
2018
10月23日,完成隧道运营系统测试,进行隧道开通前的收尾工作。
5月5日,隧道内公路全部建设完成,开始进行机电安装。
2017
8月10日,盾构最后一个吊出接收井,盾构拆卸完成。
5月3日,盾构机开始进行拆卸工作。
4月5日,盾构机顺利进入位于西雅图中心的接收井,掘进共9270英尺,拼装1426环,SR99隧道正式贯通。
2月1日,盾构机穿越Battery街隧道。
1月5日,盾构机进行了最后一次高压维护。
2016
9月12日,盾构机更换了14把刀具后恢复掘进。
9月1日,盾构机停机进行刀具检修与更换。
8月22日,盾构机掘进了4000英尺,拼装了607环。
8月1日,盾构机掘进进入第五区,共掘进了3400英尺,拼装了515环。
7月19日,盾构机共更换了33把刀具,并完成盾构机的维护检修后,恢复掘进。
6月23日,盾构机到达预定的4号维护点,开始进行定期维护。盾构机掘进3088英尺,拼装了466环,完成了整条隧道的三分之一。盾构机在维护中进行高压刀盘检查、刀具更换、机械设备检修等工作。
6月20日,盾构机掘进了2971英尺,拼装了449环。施工队开始准备下一次的盾构停机维护。
5月31日,盾构机到达西大街,掘进了2314英尺,完成了25%的隧道掘进。
5月17日,盾构机短暂停机修整后,继续掘进。盾构机掘进了2000英尺,拼装300环。
5月11日,盾构机掘进了385英尺,完全穿越阿拉斯加高架桥,并继续掘进。
4月29日,阿拉斯加高架桥正式封闭,为期两周。盾构恢复掘进,离开3号维护点,开始穿越阿拉斯加高架桥。
4月11日,盾构完成了刀具更换与日常维护,阿拉斯加高架桥准备封闭,以使盾构穿越。
3月14日,盾构掘进了1437英尺,完成了15%掘进距离后,来到3号维护点进行维护,进行机电系统检查,并在高压下更换刀具,为之后在阿拉斯加高架桥下的掘进做准备。
3月3日,盾构机开始向南华盛顿大街掘进,掘进了约110英尺。
2月23日,整改完成,盾构恢复掘进,随后掘进了25英尺,拼装了3环。
1月14日,业主责令停工整顿,盾构停机。
1月12日,盾构机路线上方出现坑洞。
2015
12月22日,盾构恢复掘进,推出抢修井外,并推进了12环。
12月14日,抢修井开始回填。
11月12日,维修后的盾构机开始进行测试。
8月25日,抢修完毕的盾构机头吊入抢修井内重新组装。
6月5日,安装新的主轴承外圈与内圈密封,对盾构进行主轴承更换并作其他维修。
3月30日,盾构机头被吊出抢修井,进行维修与零件更换。
3月2日,抢修井施工完成,盾构进入抢修井。
2014
9月2日,盾构机向前推进3英尺,到达抢修井外。
5月15日,抢修井开始挖掘。
1月29日,盾构机掘进中遭遇深井套管,再次出现高温警报,主轴承密封出现损坏,盾构停机。施工方开始制定盾构抢修计划。
1月28日,盾构恢复掘进。
2013
12月6日,盾构出现高温情况,停机158小时进行高压检查。
12月5日,盾构掘进1000英尺。
10月31日,对盾构机掘进参数进行调整,更换新刀具。
8月20日,与码头工人工会有关渣土堆运发生劳动争议。
7月20日,Betha号盾构机始发。