Tunneltalk:SR99隧道工程工期延误长达两年,但是预算不会增加
来源:Tunneltalk 发布:2017/5/19 浏览:

华盛顿交管局官方对西雅图阿拉斯加方式高架桥替代项目的财务状况进行了独立审查,得出结论认为,总体方案仍可在项目开始时设定的31亿美元预算内完成。 尽管施工延误和与TBM破裂相关的额外成本导致所有者(WSDOT)负责3.175亿美元的变更单和额外管理费用,但是目前这些费用仍在业主的预期范围之内。

An independent review of the financial position of the Alaskan Way Viaduct Replacement Project in Seattle concludes that the overall program can still be completed within the US$3.1 billion budget set at the start of the project. This is in spite of construction delays and additional costs associated with the TBM breakdown which, under a current “worst case scenario”, would result in the owner (WSDOT) being liable for $317.5 million of change orders and extra administration costs.

However, even if this worst case scenario were to play out, the independent three-person Expert Review Panel (ERP) which reports annually to the Governor and the Washington State Legislature on project progress, “remains confident” that no more State or local funds will be required, as things currently stand, to complete the project. These calculations, however, include $200 million of anticipated toll revenue raised by the completed project although the level at which this will be charged is yet to be agreed by the State Legislature.

Speaking to TunnelTalk from Seattle, ERP chairperson Patricia Galloway said the Cost Estimation Validation Process (CEVP) that WSDOT employed when it was preparing the design-build tunneling contract was proof of the owner’s “foresight” in managing project risks. Galloway explained that as part of the CEVP process WSDOT hired an advisory team of international tunneling experts to make cost projections and estimates based on risks associated with operating a “one of its kind TBM.” These recommendations formed the basis of an incentive versus risk contingency contract payment structure with the tunnel contractor, STP (the joint venture of Dragados and Tutor Perini), that was subsequently incorporated into the design-build contract by WSDOT’s California-based expert legal firm.

“The potential funding sources [to cover the extra costs that have been incurred by STP] are currently higher than the worst case scenario costs to date,” explained Galloway, “and that is because of what we believe was the foresight of WSDOT to prepare a contract and a program budget – for which the design-build tunnel contract is only one part – to make all [the project elements] work together for completion of the entire program.”

However the ERP, in its latest April 2015 report, recognizes that there are “important challenges” presented by the current and ongoing problems associated with the $1.1 billion tunnel construction contract “that may affect budget and schedule.”

The SR99 tunnel program represents 35% of the overall SR99 Viaduct Replacement Project that also includes the demolition of the viaduct and restoration of the Seattle waterfront; construction and reconfiguration of the highways to service the north and south portals; and the decommissioning of the city’s Battery Street road tunnel.

To counterbalance the potential liability associated with increased tunnel construction costs, schedule overruns beyond the contract delivery date of January 16, 2016, and costs associated with repairs to the 17.5m diameter Hitachi Zosen EPBM, the ERP notes that there are currently up to $329.6 million of funds that could be realised to cover the potential deficit as it stands at present (Fig 1). These relate to:

under-spends and unused contingencies in other parts of the overall project to an amount of some $59.2 million;

utilization of the £65 million of incentive-based contingency funds built into the design-build tunnel contract with STP;

$50 million of liquidated damages that relate to penalties of up to $50,000/day that will be levied against STP for late completion beyond the substantial contract completion date of 17 January 2016 (rising to $100,00/day after November 9, 2016), and;

the assumption of a successful maximum claim of $85 million being made against the TBM insurance policy.

The ERP’s latest financial projections are based on data made available by all the project’s stakeholders and assume that no more problems emerge once the TBM is restarted in August (2015). All potential Differing Site Conditions (DSC) contingencies and non-tunnel under-spends are accounted for in its calculations, and there now remains only $20 million of contingency in the Deformation Fund to cover possible extra costs associated with settlements and damage caused by TBM excavation operations under Downtown Seattle after the machine has passed beyond its final Safe Haven 3 at 1,500ft (457m) into the TBM tunnel drive.

“Barring no other major problems with the TBM and its operation, and knowing that the hardest part of the tunnelling will have been completed by the time STP hits Safe Haven 3 [at 1,500ft], and that there is the availability to the program of the £20 million Deformation Fund that has not been included in our calculations, once the drive goes under the city, and barring something completely unforeseeable, then there should be sufficient funds available to complete the program to the $3.1 billion budget” said Galloway.

The ERP notes, however, that the $317.5 million figure of potential extra liabilities relating to STP’s accumulated claims for extra costs that it has so far incurred is a “worst case scenario”, adding that “the ERP’s experience is that awards of contractors’ claims is often substantially less than the sums requested by them.” If STP fails to recover these substantial extra costs from WSDOT – either through mutual agreement or following intervention by the DRB, or via possible future legal challenges in court – it is (so far) looking at a potential cost addition of 26.5% above its contract price of £1.1 billion, not including any successful claim made against the maximum $85 million TBM insurance policy.

To date STP has submitted, or is due to submit, $292.5 million of change order requests, which it is entitled to do under the terms of the design-build contract. This includes the largest single claim to date, known as PCO (Potential Change Order) 250, which relates to excavation of the recovery shaft and damage to the TBM that STP claims was caused by an old and unmapped 8in diameter steel well casing. That claim has been the subject of a mass of correspondence since it was lodged in December 2013, shortly after the TBM was stopped. WSDOT and STP have failed to reach agreement on the issue, and a Dispute Review Panel is now due to convene shortly to hear evidence from both parties. However, under the terms of the contract between STP and WSDOT the panel’s recommendations are not binding upon either party.

Three main elements emerge from the latest ERP report:

the disputes review process is not working “due to both parties’ reluctance to acknowledge the decisions made in the process” (p21 of the official report attached)

the contingency and project risk provisions built into the design-build contract are working well to minimize project financial risk and to protect the State’s liability

there exists “a tendency [for owner and contractor] to blame rather than to work together to solve problems” (p21 of the report)

Galloway told TunnelTalk that a significant amount of work had been carried out by STP towards completing other elements of the tunnel contract that had originally been scheduled to take place following completion of the TBM excavation drive. These include works at the north and south portals, which are now substantially complete, and internal structures inside the tunnel behind the TBM. “The fact that STP has been able to advance a lot of that work and take advantage of the TBM downtime has enabled it to mitigate a significant portion of the delay.” Galloway also pointed out that talk of a two-year delay was “a bit of a misnomer” because while STP’s project completion date assumed completion with no risks being realized by the end of 2015, WSDOT’s less demanding schedule incorporated an extra year’s worth of project risk to November 2016.

“Through the Cost Estimating Validation Process (CEVP), the WSDOT contract contemplated that there might be issues, since this was to be a first of its kind machine, and that there was the potential for issues with the TBM,” explained Galloway. “That is why the insurance was set up in such a way so as to deal with some of the issues that have, since, occurred; a claim has been made and the insurance investigators are out on site doing their investigation work."

“The next round of excavation to Safe Haven 3 [about 400ft ahead once the repaired TBM restarts] will be important in terms of seeing how the machine operates after the repairs, but the good news is that STP is meeting its repair schedule.” Once an expert analysis of the advance rate being achieved by the newly reinforced and repaired machine during its short drive into Safe Haven 3 is complete, and following a final inspection of the TBM prior to driving under Downtown, STP is expected to announce a revised substantial completion date. WSDOT’s reduction by £8 million of the maximum $58 million liquidated damages that it can hold STP liable for (to cover schedule overrun penalties) implies a current estimate of an extra 160 days at $50,000/day – some time in June-July 2017.

This analysis, however, presupposes no further problems being encountered since most of the sources for offsetting income and contingency have now been accounted for. In addition, although liability for the extra costs might not fall upon WSDOT (and ultimately the taxpayers of Seattle) if the owner can successfully fend off all, most, or some of the change order claims, the contractor could be facing huge additional costs over and above its £1.1 billion contract price.

Next week TunnelTalk will report on the issues surrounding the major change order PCO250 – which relates to the TBM obstruction – based on a mountain of project correspondence between WSDOT and STP that has been released to us under the USA Freedom of Information legislation.

隧道网版权及免责声明:

凡本网注明“来源:隧道网”的所有作品,版权均属于隧道网,未经本网授权,不得转载、摘编或以其它方式使用上述作品。已经本网授权使用作品的,须在授权范围内使用,并注明“来源:隧道网”。违反上述声明者,本网将保留追究其相关法律责任的权利。凡本网来源注明为非隧道网的作品,均转载自其它媒体,转载目的在于传递更多信息,该文章仅代表作者观点,并不代表本网赞同其观点或对其真实性负责,请读者自行核实相关内容,仅作参考。如因作品内容、版权和其它问题请与本网联系。

相关文章
大事记
BIG EVENT
2019
2月2日,SR99隧道正式开通。
2018
10月23日,完成隧道运营系统测试,进行隧道开通前的收尾工作。
5月5日,隧道内公路全部建设完成,开始进行机电安装。
2017
8月10日,盾构最后一个吊出接收井,盾构拆卸完成。
5月3日,盾构机开始进行拆卸工作。
4月5日,盾构机顺利进入位于西雅图中心的接收井,掘进共9270英尺,拼装1426环,SR99隧道正式贯通。
2月1日,盾构机穿越Battery街隧道。
1月5日,盾构机进行了最后一次高压维护。
2016
9月12日,盾构机更换了14把刀具后恢复掘进。
9月1日,盾构机停机进行刀具检修与更换。
8月22日,盾构机掘进了4000英尺,拼装了607环。
8月1日,盾构机掘进进入第五区,共掘进了3400英尺,拼装了515环。
7月19日,盾构机共更换了33把刀具,并完成盾构机的维护检修后,恢复掘进。
6月23日,盾构机到达预定的4号维护点,开始进行定期维护。盾构机掘进3088英尺,拼装了466环,完成了整条隧道的三分之一。盾构机在维护中进行高压刀盘检查、刀具更换、机械设备检修等工作。
6月20日,盾构机掘进了2971英尺,拼装了449环。施工队开始准备下一次的盾构停机维护。
5月31日,盾构机到达西大街,掘进了2314英尺,完成了25%的隧道掘进。
5月17日,盾构机短暂停机修整后,继续掘进。盾构机掘进了2000英尺,拼装300环。
5月11日,盾构机掘进了385英尺,完全穿越阿拉斯加高架桥,并继续掘进。
4月29日,阿拉斯加高架桥正式封闭,为期两周。盾构恢复掘进,离开3号维护点,开始穿越阿拉斯加高架桥。
4月11日,盾构完成了刀具更换与日常维护,阿拉斯加高架桥准备封闭,以使盾构穿越。
3月14日,盾构掘进了1437英尺,完成了15%掘进距离后,来到3号维护点进行维护,进行机电系统检查,并在高压下更换刀具,为之后在阿拉斯加高架桥下的掘进做准备。
3月3日,盾构机开始向南华盛顿大街掘进,掘进了约110英尺。
2月23日,整改完成,盾构恢复掘进,随后掘进了25英尺,拼装了3环。
1月14日,业主责令停工整顿,盾构停机。
1月12日,盾构机路线上方出现坑洞。
2015
12月22日,盾构恢复掘进,推出抢修井外,并推进了12环。
12月14日,抢修井开始回填。
11月12日,维修后的盾构机开始进行测试。
8月25日,抢修完毕的盾构机头吊入抢修井内重新组装。
6月5日,安装新的主轴承外圈与内圈密封,对盾构进行主轴承更换并作其他维修。
3月30日,盾构机头被吊出抢修井,进行维修与零件更换。
3月2日,抢修井施工完成,盾构进入抢修井。
2014
9月2日,盾构机向前推进3英尺,到达抢修井外。
5月15日,抢修井开始挖掘。
1月29日,盾构机掘进中遭遇深井套管,再次出现高温警报,主轴承密封出现损坏,盾构停机。施工方开始制定盾构抢修计划。
1月28日,盾构恢复掘进。
2013
12月6日,盾构出现高温情况,停机158小时进行高压检查。
12月5日,盾构掘进1000英尺。
10月31日,对盾构机掘进参数进行调整,更换新刀具。
8月20日,与码头工人工会有关渣土堆运发生劳动争议。
7月20日,Betha号盾构机始发。